Emergency: Virtualisation patch replacement

Scheduled Maintenance Report for Evolve IP UK

Completed

The scheduled maintenance has been completed.
Posted Mar 26, 2025 - 02:00 GMT

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Mar 25, 2025 - 22:00 GMT

Scheduled

Reason:
Evolve IP will be re-patching 2 hosts in its virtualisation platform

Impact:
No impact expected - These hosts will be drained of production VMs prior to work being completed. They will be tested prior to the hosts being placed back into the production cluster.

Checks:
Complete iSCSI test plan (ping both SAN interfaces with Jumbo Frames) ensure the interface is up. We are testing the host in a test cluster eith a VM to ensure that the VM can see its storage on the SAN post change.

Rollback:
Revert to previous config

User actions:
No User actions required
Posted Mar 21, 2025 - 15:58 GMT